Saturday, August 7, 2010

Day16 - Hammers and Nails

It seems like Friday's are the busy days for our Site Supervisor.  Our frame was delivered on Thursday with work starting Friday on our framing.  Our Site Supervisor also called on Friday to give us our weekly update.  
 
Framing will continue for the next couple of days with the roof trusses being delivered early next week to be completed by the end of next week....that is if the rain holds out.  I don't generally trust weather forecasts but the next few days are supposed to bring -
Monday            Possible shower                        Max 22
Tuesday           Showers increasing to rain       Max 20
Wednesday      Rain clearing                            Max 21